02 / STAGE LEDGER
Each stage and what governs its duration
01 — Demolition and waste removal
Governed by access and disposal. A ground-floor room with a driveway strips out faster than a first-floor or apartment bathroom where every load travels by lift and booked dock time.
02 — Structural and substrate repairs
The unknown stage. Rotted framing, failed sheeting or an uneven slab only appear once the room is open, and repairs must be finished before any new sheeting or falls are set.
03 — Plumbing and electrical rough-in
Driven by how far services move. Keeping the layout puts pipes back near existing points; relocating a toilet or moving to a wall-hung basin means new runs, new penetrations and coordination between two trades.
04 — Sheeting and screeding
Wet-area sheeting goes up, then falls are formed to the waste. Screed needs to set before anything is applied over it, so this stage carries its own built-in pause.
05 — Waterproofing and cure
Bond breakers, corners and penetrations are detailed first, then coats are applied in sequence. Cure time between coats and before tiling is set by the product data sheet and site conditions — not by the schedule. Read the
waterproofing guide or the
membrane service page.
06 — Tiling and grouting
Usually the longest single stage. Large-format slabs, mitred edges, mosaic floors, niches and pattern set-outs all add hours, and adhesive must set before grout goes in. See
bathroom tiling.
07 — Fit-off: fixtures and tapware
Toilet, basin, mixers, rail and waste are installed and tested. Quick work — provided every item is on site. A single missing mixer holds the whole fit-off open.
08 — Shower glazing (measured after tiling)
Glass is measured to the finished tiled surface, not to the frame, because walls are rarely perfectly plumb. That measure can only happen once tiling is complete, and fabrication then adds its own lead time. It is the most common reason a bathroom looks finished but is not. See
walk-in showers.
09 — Joinery installation
Vanity, shaving cabinet and any tall storage are scribed and fixed, with stone tops templated to the installed cabinet where required. See
vanity installation.
10 — Painting, silicone and final clean
Ceilings and any painted surfaces are cut in, junctions siliconed, then the room is cleaned and handed over with a defect walk-through. Silicone needs curing time before the shower is used.